ASHP case study 1

Mid-Suffolk Leisure Centre

Public contract for 300KW air source heat pump, as part of the leisure centre's action plan following them declaring a climate crisis in 2019.

Pump size: 300KW

Estimate your project

What we did


  • The challenge was to introduce a super high efficiency large space warming heating system.
  • To create this, a 300kW air source heat pump was installed with a 4,000 litre buffer vessel.
  • A new mini package plantroom was also introduced.
  • Along with a new 108mm crimped stainless steel pipework setup, including external ground work and all fabric duct installation.
  • 100M electrical supply of 400amp was provided to supply power to the plant.

Other project images

Client review

References are available on request for this commercial client